WASCO Island Network Update for August 9, 2016

WASCO Island Network Update for August 9, 2016

The Water and Sewerage Company Inc. (WASCO) wishes to advise of actions and schedule for communities in the Southern part of the island, for today Tuesday 9th August  2016
1.      CANARIES SYSTEM
Ø  Main Canaries Primary System: In operation
Ø  Anse la Verdue:  In operation

2.      SOUFRIERE SYSTEM
Ø  Ruby: In operation (river source in operation; spring source in operation)
Ø  Fond St. Jacques 1: Slight increase in flows at intake, due to construction of another intake
Ø  Fond St. Jacques 2: In operation
Ø  Diamond 1: In operation
Ø  Diamond 2: In operation
Ø  Bouton: In operation

3.      CHOISEUL SYSTEM
Ø  Delcer: In operation
Ø  Saltibus Upper: In operation
Ø  Saltibus Lower: In operation
Ø  Toucousson: In operation

4.      VIEUX FORT SYSTEM
Ø  Grace: In operation
Ø  Beausejour: All areas being fed from Grace system

5.      MICOUD
Ø  Micoud Primary system: In operation
Ø  Patience:  In operation
Ø  Belle Vue: In operation
Ø  Desruisseaux: In operation

6.      DENNERY
Ø  Errard: In operation
Ø  Thomazo: In operation
Ø  Aux Lyon: In operation
Ø  Derniere Riviere: In operation
All other communities are being served, whilst we will maintain the supply of water to the aforementioned areas, there may be inconsistencies due to demand or damages which may occur on the lines.