One year after the rebuilt St Jude Hospital was handed over to the Ministry of Health, the Government is now projecting a full transition to the facility sometime in 2027, after an earlier target to complete the process this year was missed.
Today, November 16, marks the one-year anniversary of the handover, which was meant to start a phased return of services to the hospital. Within the first seven to eight months, administration, kitchen and laundry services, physiotherapy and dialysis had all begun operating from the site.
The Government had also been hopeful that the full transition could be completed by the summer. In April, Health Minister Moses Jn Baptiste said the hospital could be fully transitioned within three to four months.
That timeline came and went.
Now, 12 months into the commissioning process, Jn Baptiste says the full transition is expected sometime in 2027, although he is not giving a firm date.
“We do not have an exact timeline. I can’t tell you it is two weeks or three weeks,” he said at Monday’s pre-Cabinet press briefing. “But we are convinced and committed, based on everything we are seeing, that within a reasonable time in 2027 next year, we will completely transition the hospital.”
The St Jude Hospital project remains one of the most closely watched public projects in Saint Lucia after a reconstruction process stretching back nearly two decades.
The original hospital was destroyed by fire in 2009, forcing services into the George Odlum Stadium. Since then, delays, changes in plans and repeated opening projections have kept the project under intense public scrutiny.
Jn Baptiste acknowledged that the latest phase has taken longer than anticipated.
“It is very clear that the full verification, the safety checks and all of that has taken some more time than we anticipated,” he said.
He explained that as the commissioning process moved forward, specialists and experts assisting with the transition identified additional processes and adjustments that needed to be completed before the hospital could fully open.
Some of these include further verification and testing of electrical and water systems, medical gases, ventilation, radiation-related systems and other medical equipment. Staff also have to be trained on new equipment, new layouts and safety procedures.
Jn Baptiste stressed, however, that the issue is no longer the construction of the hospital itself.
What remains, he said, is making sure those systems are properly tested and verified before more departments are moved.
“What we don’t want to do is to rush a transition that is not safe for the patients and to rush a transition that does not have full verification,” Jn Baptiste said.