Marchand Main Road Rehabilitation Scheduled For Completion This Week

The Department of Infrastructure, Ports and Transport wishes to inform the general and motoring public that completion of the rehabilitation of the Marchand Main road is scheduled for Tuesday 6th December, 2022.

These works will include the placement of the final layer of asphalt.

As a result, the Marchand Main Road will be closed to motorists throughout the duration.

Access through Rockhall will be permitted, but  the public is advised to utilize alternative routes to avoid delay.

There is a possibility of the works continuing into Wednesday 7th December, 2022.

 The Department of Infrastructure, Ports and Transport regrets any inconveniences caused as a result of the upcoming works.

SOURCE: Department of Infrastructure, Ports and Transport. Headline photo: Stock image

Any third-party or user posts, comments, replies, and third-party entries published on the St. Lucia Times website (https://stluciatimes.com) in no way convey the thoughts, sentiments or intents of St. Lucia Times, the author of any said article or post, the website, or the business. St. Lucia Times is not responsible or liable for, and does not endorse, any comments or replies posted by users and third parties, and especially the content therein and whether it is accurate. St. Lucia Times reserves the right to remove, screen, edit, or reinstate content posted by third parties on this website or any other online platform owned by St. Lucia Times (this includes the said user posts, comments, replies, and third-party entries) at our sole discretion for any reason or no reason, and without notice to you, or any user. For example, we may remove a comment or reply if we believe it violates any part of the St. Lucia Criminal Code, particularly section 313 which pertains to the offence of Libel. Except as required by law, we have no obligation to retain or provide you with copies of any content you as a user may post, or any other post or reply made by any third-party on this website or any other online platform owned by St. Lucia Times. All third-parties and users agree that this is a public forum, and we do not guarantee any confidentiality with respect to any content you as a user may post, or any other post or reply made by any third-party on this website. Any posts made and information disclosed by you is at your own risk.

2 COMMENTS

  1. So it looks like machard is the only road the needs attention just a few months ago they repaved the whole stretch of road so what happen to the other communities and highways that need this attention, something is very wrong with this government

  2. The road was already completed back in August!!!

    However, the contractor did a very poor job and pot holes appeared literally days later. To save face, the government lied and said that the works were not complete when people started to complain. The contractor had already pulled off all equipment from the site since the work was finished and every now and then, potholing works were being done by the government to patch his shoddy work.

    Right now, it’s another set work to repair the poorly resurfaced road that’s taking place. In other words, two sets of money is being paid to do one job. This is ridiculous. They really think people are stupid. I know a thing or two about road works. I worked on the Castries to Gros Islet Highway years ago.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

TRENDING

Subscribe to our St. Lucia Times Newsletter

Get our headlines emailed to you every day.

Share via
Send this to a friend